NCCCO MOBILE CRANE EXAM -
100 QUESTIONS AND CORRECT DETAILED ANSWERS
VERIFIED ANSWERS GRADED A+
- What action does a signal person intend the operator to perform if he extends his arm at shoulder
- Boom down
- Swing
- Boom up
- Extend boom - ansc.
height, makes a fist with his hand, and sticks his/her thumb up?
- Where must the operator's manual be kept during crane operations?
- The operator's manual must be kept in a location that is readily available
- The operator's manual must be kept in the cab at all times
- The operator's manual must be kept in the dispatch office
- The operator's manual must be kept in a secure place - ansb.
- According to ASME B30.5, what are the minimal requirements to meet crane operator
- High School Diploma
- CDL with on the job training
- Physical, Written Test, Practical Test
- CDL physical, employers written permission - ansc.
qualifications?
- When hoisting personnel, within what percentage of level must a telescopic boom crane be in order for
- 1%
- 2%
- 5%
- 8% - ansa.
the gross ratings in the load chart to remain valid?
- The load line of the crane you're operating contacts an energized power line. There's no sign of any
- Climb down carefully from the crane cab
- Jump down, feet together
- Stay in the cab until the lines are de-energized
- Get as far away from the crane as possible - ansc.
other danger, such as fire. What should you do?
- What hand signal must be obeyed at all times?
- Swing
- Clog-everything
- Stop
- Hoist Slow - ansc.
- According to OSHA 1926.1413, how many randomly distributed broken wires in rotation-resistant rope
- 1 broken wire in 6 rope diameters
- 2 broken wires in 30 rope diameters
- 3 broken wires in one strand in one lay
- 2 broken wires in 6 rope diameters - ansd.
are cause for replacement of the rope?
- When removing pins or bolts from a boom assembly, workers shall remain
- clear of sledge hammers 1 / 3
NCCCO MOBILE CRANE EXAM -
100 QUESTIONS AND CORRECT DETAILED ANSWERS
VERIFIED ANSWERS GRADED A+
- out from under the boom
- on top of boom holding pendants
- in sight of the operator - ansb.
- What is the net capacity of a crane on main boom unless the manufacturer states otherwise?
- The capacity listed in the load chart minus the weight of the rigging and all attachments
- The capacity listed in the load chart plus the weight of the rigging and all attachments
- The capacity listed in the load chart minus the weight of the rigging and all attachments not in use
- The capacity listed in the load chart minus the weight of the rigging alone - ansa.
- When may a crane be overloaded?
- When the supervisor says it's OK
- Never
- When testing the crane
- When proof testing a man basket - ansc.
- What may happen to a properly rigged load when lifted off the ground unless the operator takes
- It could swing out away from the crane
- It could swing in towards the crane
- It could raise absolutely vertically
- It could shift in its rigging - ansa.
account of boom deflection?
- When can the operator leave the crane?
- Break time
- End of the shift
- After securing the crane
- When a storm is coming - ansb.
- What Standard Method hand signal is being illustrated?
- Swing
- Stop
- Emergency Stop
- Travel - ansa.
- When can a crane be side loaded?
- Dragging a load
- With a freely suspended load
- Never
- Pile-driving - ansb.
- The deflection of a boom will cause the load to?
- side load the boom
- increase the radius
- have no effect - ansc.
b.decrfrease the radius
- Who should an operator respond to a "stop" signal from? 2 / 3
NCCCO MOBILE CRANE EXAM -
100 QUESTIONS AND CORRECT DETAILED ANSWERS
VERIFIED ANSWERS GRADED A+
- Appointed signal person only
- Project manager only
- Superintendent only
- Anyone - ansd.
- When should tag lines be used?
- Always
- Always, except when the use of the tagline become hazardous
- Ehen the rotation of the load becomes hazardous
- When the operator cant see the load - ansc.
- Which area do truck cranes without a 5th outrigger generally have no lifting capacity unless the
- The side
- The rear
- The front
- The outriggers - ansc.
manufacturer states otherwise?
- What is the definition of "operating radius?"
- The distance from the base of the boom to the center of the load b. The distance from the front of the
- The distance from the center of rotation of the crane to the center of the load
- The distance from the center of rotation of the crane to the center of gravity of the load - ansd.
crane to the center of gravity of the load
- What shall be in the operators cab during crane operations?
- load charts
- Inspection reports
- Hand signal chart
- The crane log - ansa.
- What applies to the capacities below the bold line shown on a load chart?
- They are based on the structural strength of the crane
- They must not be used
- They are based on the stability of the crane
- They should only be used if the crane is set up on outriggers - ansc.
- Which of the following is considered duty cycle work?
- Pile- driving
- Setting trusses
- Clam - Shell digging
d Unloading trucks - ansc.
- In which quadrant are rough terrain crane capacities generally greater?
- Over the front
- Over the rear
- Over the right side
- Over the left side - ansa.
- When doing cycle work, the load chart must be reduced by how much?
- / 3